The new Naples Pier is coming along quickly. On September 18, Shoreline Foundation finished the concrete pour for the mid-pavilion, which took the project past the halfway mark on concrete for the whole pier. The Naples Daily News, writing on October 1, gives July 2027 as the expected completion date. That means people should be walking out over the Gulf again sometime in mid-2027.
One part of the old pier is staying gone. On March 4, Naples City Council voted unanimously to rebuild without permanent food concessions and without outdoor dining. A portable cart for water, ice cream and soda is the most the city is still considering. The construction fences have already moved the food side of a beach morning off 12th Avenue South and into the blocks nearby. Those fences come down next summer, but the food at the pier will not come back with them.
What ended at the end of 12th Avenue South
The pier has sold food since 1946. Cosmos at the Pier held the restaurant lease starting in 2015, selling pizza, hot dogs, drinks and beach supplies. That brought the city about $100,000 a year.
Two things ended that run. In July 2024, after reviewing survey results, Council agreed by consensus that concessions were unnecessary. Members said a food stand could crowd the pier entrance and bring noise and odors to the homes right next to it. Then FEMA said neither the old Cosmos restaurant nor any other permanent concession stand would be allowed above the water under its newer risk guidelines. FEMA's position carries weight because federal money is paying for part of the rebuild. The agency committed funding in December 2025, and the Naples Daily News puts the grant at $11.4 million.
Council did not agree on everything. Here is the exchange from the March 4 meeting.
"Mark my words, if we don't have concessions, we are going to get lambasted by our residents and our tourists." Council member Berne Barton, arguing for a food cart before the vote
Council member Bill Kramer, who represents the city on the county Tourist Development Council, gave the opposite view. He said most of the locals he knows bring their own food and drinks rather than pay concession prices, and that permanent concessions should not return. Council member Linda Penniman supported a cart, as long as it does not compete with local businesses nearby. City Manager Gary Young said there is no room for a food truck, so a portable cart is the only option. FEMA would not stop a cart from operating on the pier. The city plans to run electrical power to the land-side area so a cart could plug in. No vendor has been named.
The money works out without the lease. Young told Council the city already gets an annual $500,000 Tourist Development Council grant for upkeep and operations at the pier and the beach ends. Beach parking revenue and beach funds pay for pier maintenance as well. So the roughly $100,000 a year from Cosmos was never what kept the pier running.
What the new entry will have instead
MHK Architecture's third design shrinks the buildings at the pier entrance and puts that space toward functions other than food. Architect Maureen Minker took Council through the changes. Together with the design memo, the plan includes:
- North building. The men's restroom at the pier entry gets a small beach patrol office with its own bathroom, a family restroom, and a rear room that used to be for changing and is now pier storage.
- Police and patrol space. The north-side building has a smaller police and beach patrol station, an ADA-accessible restroom, turtle-safe observation glass, and work space for camera monitoring.
- South side. The women's restrooms stay, with a new shade structure and benches outside. The showers move out of the shaded area.
- On the pier. An underwater camera will let visitors watch marine life.
The structure is being built higher and stronger than the old one. The new deck sits at least three feet higher. The pilings are thicker, and the ipe wood decking rests on more concrete support. The design also uses fewer pilings, spaced farther apart, to reduce the effect on the beaches on either side. Gulfshore Business reports the total project cost as $26.3 million. The construction contract with Shoreline Foundation alone was $23.5 million when the city awarded it in October 2024.
How far along the work is, by the city's own log
The city's project page keeps a running log of construction. The 2026 entries show where the work stands:
- January 5 and 6. Groundbreaking ceremony, then construction begins the next day.
- April 13. Demolition of the old pier is finished.
- April 24. Fifty-nine old concrete pilings are sunk at Wasmer Reef, adding to an artificial reef first started in 2015.
- June 17. Crews start building a trestle along the south side so work can keep going when weather sends the offshore barges in to shelter.
- June 26. First concrete pour for the bents, about 20 yards out of roughly 602 yards needed for the whole job.
- July 24. Third pour finished, about 200 cubic yards in total, with two-thirds of the ipe decking delivered.
- September 18. Mid-pavilion pour finished, taking the concrete work past 50%.
The order of work also tells you what the pier will look like this season. The city says Shoreline Foundation will start laying the ipe deck only after all the concrete is poured. Through the winter, the view from the beach will be mostly concrete and barges, not a finished walkway. The city's page still gives no public reopening date. July 2027 is the newspaper's estimate, not a date the city has announced.
People are already watching from the sand. WINK News updated a progress report on September 30. In it, beachgoers said they missed fishing off the pier.
The beach end as it works this season
The city has closed the pier, its stairs, restrooms and showers, and 12th Avenue South west of Gulf Shore Boulevard South. Only the western third of the pier parking lot at 12th Avenue South and Gulf Shore Boulevard South is open. The eastern two-thirds are a construction yard. Pedestrian bypasses at the Broad Avenue South and 13th Avenue South beach ends stay open through the project, and both have restrooms. Back in March, the Naples Daily News reported that some beachgoers objected to the temporary toilets and that the city was working on a longer-term fix.
The Broad Avenue bypass is close to the newest business in the area. The Olde Naples Hotel at 200 Broad Avenue South opened May 15 with 109 rooms and Annie's Bistro, Bar & Bakery on site. The operator's website now lists the hotel's Tammy Fender Holistic Spa as open too. At the other end of 12th Avenue South, the Naples City Dock at 880 12th Ave. S. in Crayton Cove is still listed as a full-service marina with fuel, pump-out, bait, refreshments and charters.
The calendar a few blocks inland
Third Street South and Fifth Avenue South are where the area's scheduled events happen this fall. Several dates fall in the next five weeks:
- Saturdays through October 31, 7:30 to 11:30 a.m. The summer version of the Third Street South Farmers Market sets up behind Tommy Bahama.
- October 8, 6:30 to 9:30 p.m. Evening on Fifth brings live music to the sidewalks, with dining and shopping along Fifth Avenue South.
- October 15 to 18. The French-themed Bon Marché Sidewalk Sale on Third Street South, with more than 25 businesses taking part.
- October 31. The Fifth Avenue South Halloween Spooktacular runs from 3 to 5 p.m. in Cambier Park, followed by Halloween Evening on Fifth with live music along the avenue from 5 to 8 p.m.
- Starting November 7, 7:30 to 11:30 a.m. The farmers market moves back onto Third Street South between Broad Avenue South and 13th Avenue South, using part of 12th Avenue South too. It runs every Saturday except March 13, 2027.
The November 7 move puts the city's busiest Saturday morning event on the same three streets that lead to the pier. Next summer, a walk out to the end of the rebuilt pier will start and finish a few blocks from the market stalls. There will be no snack bar out over the water, and the closest food will be on Third Street South, Broad Avenue South, and whatever cart the city ends up approving.
If you own near 12th Avenue South or the Broad Avenue beach end and want to know how the pier's return, the new entry buildings and the shrunken parking lot affect your street, Chadwick Knight can walk you through it. Request your free home valuation or market consultation.